WhateverLab/Umbau: Unterschied zwischen den Versionen

MariusKintel (Diskussion | Beiträge)
Die Seite wurde neu angelegt: = Umbau = Due to economic constraints, we're aiming to perform the renovation in multiple phases. After a long time of inactivity, Phase 1 was officially kicked off 25...
 
Fin (Diskussion | Beiträge)
 
(42 dazwischenliegende Versionen von 2 Benutzern werden nicht angezeigt)
Zeile 27: Zeile 27:
Costs:
Costs:


We already have most of the equiment and material necessary, so only minor supplements are needed.
We already have most of the equiment and material necessary, so only minor supplements are needed (Putz, Tiefengund, Spachtelmasse, misc. tools)


* Putz, Tiefengund and Spachtelmasse: FIXME
=== Floor ===
* Misc. tools: FIXME
 
Bericht Bodenberatung durch Herrn Aschenbrenner / [http://www.industriefussboden.at/ Fa. AIB GmbH] von Mo.
 
: für Epoxid zu viele Unebenheiten, vor allem haben die Holzplatten zu viel Spiel (und hier sind nicht vereinzelte Problemstellen gemeint): '''nicht ordentlich machbar''' (nein, Armierung mit vertretbaren Mengen Glasfaser hilft nicht)
: Alternative: '''Anstrich''' -> DIY
: * Leihgebühr Bodenschleifmaschine Servo: EUR 22,-/Tag (exkl. MWSt)
: * Schleifpapier EUR 18,-/Stk. (exkl. MWSt), doppelseitig nutzbar (1 Stück sei ausreichend)
: * 1. Anstrich: [http://www.industriefussboden.at/website/astrochem/mat_undercoat.htm ''astrochem'' Grundierung/Imprägnierung] fuer 10 kg ~40m² ... EUR 139,- (exkl. MWSt) [Erstanstrich braucht mehr Material]
: * 2. + 3. Anstrich: [http://www.industriefussboden.at/website/astrochem/mat_sealing_uv.htm ''astrochem'' Versiegelung UV] (Farbe) 10kg fuer 2x 40m² ... EUR 179,- (exkl. MWSt)
: : Kosten ueber den Daumen EUR 15,-/m² (beinhaltet zumindest 1. und 2. Anstrich)<br>: Kosten Anstrich: (139 + 179) * 1.2 = 381.60 EUR<br>: Kosten gesamt: (22 + 18 + 139 + 179) * 1.2 = '''429.60 EUR'''
Fa. Astrochem: Tel: <code>02235/ 875 55</code> (29.3.2007) ''"Lieferzeit braucht jetzt sicher einen Monat."'' -- "Warum!? Hr. Aschenbrenner hat - um auf der sicheren Seite zu sein - von 14 Tagen gesprochen. Im Astrochem Datenblatt steht "Bei allen anderen Farben ist mit einer Lieferzeit von ca. 10 Tagen zu rechnen." -- Tja, es kam erst eine groessere Lieferung aus .fr (?) und bei so einer Kleinmenge muessten wir dann die Mehrkosten durch den Versand uebernehmen. Gibt Bescheid was das kostet. Noch nicht bestellt. (Unser -mit Abstand- [[Diskussion:HappyLab:History|zweitgereihter Farbton]] RAL 6021/Blassgruen wär' uebrigens lagernd.) --[[Benutzer:Pk|PK]] 15:58, 29. Mär. 2007 (CEST)


=== Floor ===
: Trockenzeit abhängig von der Raumtemp., mit 2 Tagen pro Anstrich rechnen, Grund und Versiegelung beinhalten Lösungsmittel, Tür zum Hauptraum gut abdichten und hofseitig begehen, bis zur Wand streichen/rollen, PVC Sesselleise erst nachher
: 4 verschiedene Farben lagernd ([[User:Philip|Philip]]: ''"wenig sexy"''), Lieferzeit anderer Farben (zB. Weiss) max. 14 Tage. eventuell bissl Flitte^W Feenstaub einstreuen


We haven't decided on a solution yet, but we're currently
Misc costs: Parkett Fugendicht, Montageschaum, ca. 50 euro
investigating an epoxy-based coating solution.


=== Electricity ===
=== Electricity ===


Ideally, we should subdivide the lab into at least 3 indepentant
The WEL will be subdivided into 2 independent circuits wired from the fuse cabinet in the corner, one will serve power for the heavy machinery lab, and one for the remaining power and lights.
circuits. The main reason for this is that short circuits are more
likely to happen in an electronics lab than anywhere else. In
addition, the future machine room will draw a lot of power, so it
should have a dedicated circuit.
 
We might be able to reuse some cable canals inside the walls. If not,
we'll wire the circuits externally.


A generous amount of outlets has to be provided for the work places
All wiring will be done "aufputz", since the quality of the wiring inside the walls are questionable.
due to the amount of electronic apparatus being used.


Lighting should be neutral and bright.
Lighting should be neutral and bright and without too much flickering (e.g. neon with EVG).


== Phase 1 Tasks ==
== Phase 1 Tasks ==
Zeile 66: Zeile 68:
  |-
  |-
  |Repair holes & cracks with Putz and Spachtelmasse
  |Repair holes & cracks with Putz and Spachtelmasse
  | 90%
  | 100%
  |
  |
  |-
  |-
  |Scrape off loose paint & prepare surface with Tiefengrund
  |Scrape off loose paint & prepare surface with Tiefengrund
  | 50%
  | 100%
  |
  |
  |-
  |-
  |Paint all walls and ceiling
  |Paint all walls and ceiling
  | 50%
  | 100%
  |
  |  
  |-
  |-
  |Final touch
  |Final touch
| 100%
  |  
  |  
|
|}
|}


Zeile 91: Zeile 93:
  |-
  |-
  |Make a decision on the floor coating
  |Make a decision on the floor coating
  |  
  |100%
  |
  |
  |-
  |-
  |Build the missing piece just after the doorstep
  |Build the missing piece just after the doorstep
  |  
  | 100%
|
|-
|Strengthen weak spots in the floor
| 100%
  |
  |
  |-
  |-
  |Fill all cracks
  |Fill all cracks and edges
| 100%
  |  
  |  
|
  |-
  |-
  |Sand down the floor to make it even
  |Sand down the floor to make it even
  |  
  |100%
  |
  |Hopefully it's even enough now..
  |-
  |-
  |Apply coating
  |Apply coating
  |  
  | 100%
  |
  |
  |-
  |-
  |Final touch
  |Final touch
  |  
  | 100%
  |
  | Ready to rumble!
|}
|}


Zeile 124: Zeile 130:
  |-
  |-
  |Evaluate the state of the current wiring
  |Evaluate the state of the current wiring
  |  
  |100%
  |
  |Existing in-wall wires should be cut off and forgotten about
  |-
  |-
  |Decide on techincal solution wrt. circuits, fuses, earth leakage breaker etc.
  |Decide on technical solution wrt. circuits, fuses, earth leakage breaker etc.
  |  
  |100%
  |
  |We have 3 x 16A + a FI dedicated to the WEL already in place
  |-
  |-
  |Decide on lighting solution
  |Decide on light & power solution
  |  
  |100%
  |
  |
  |-
  |-
  |Aquire the necessary equipment (lamps, cables, channels, outlets, switches etc.)
  |Aquire the necessary equipment (lamps, cables, channels, outlets, switches etc.)
  |  
  |100%
  |
  |([http://www.orion.co.at/de/docs/stores/at/w1070.htm source for library/WEL lamps])
  |-
  |-
  |Build
  |Build
  |  
  |100%
  |
  |
  |-
  |-
  |Final touch
  |Final touch
  |  
  | 100%
  |
  |
|}
|}


= Plans & Ideas for Further Phases =
= Further Phases =
 
* Make heavy machinery lab closable to limit dust -> done (new room)
* More outlets in the remaining corners of the lab -> partially done
* Permanent network cabling -> done
* More (and orderly) shelving
* Fixed and labeled positions for oszis, soldering stations, etc
* Stairs to the big window (since Hvy Mchnry exit will be unusable for a while)
 
 
 